Wuxi Mcway Equipment Technology Co., LTD

Wuxi Mcway Equipment Technology Co., LTD

Testing method and process of finned tube

2022 09/29

During operation, before on-site detection, measure the delay time from the acoustic detector to the receiving system, and calculate the acoustic time correction value. During measurement, the transmitting and receiving probes shall rise and fall synchronously at the same elevation or maintain a fixed elevation difference. The distance between measuring points is 40cm, and it will be densified to 20cm in case of abnormality

The fin tube selects the appropriate transmitting voltage and amplifier gain, which remain unchanged during the retest. Display and record the time history curve of the received signal in real time. Take two finned tubes as one detection section for full combination, and complete detection for multiple sections respectively.

When using finned tubes, after each group of test tubes is tested, 10% of the test points shall be sampled randomly and repeatedly during operation, and the relative standard deviation of sound time shall not be greater than 5%; The relative standard deviation of wave amplitude shall not be greater than 10%. Regularly check whether the finned tubes are complete and whether there are sediments, coke, rust layer and other scales attached, and immediately clean them. At the same time, it is also necessary to check whether each fin tube is tightly bonded to the rubber gasket and whether the rubber gasket itself is intact to avoid leakage caused by rubber gasket degumming and damage.

The instrument adjustment of finned tube shall be in the charge of a specially assigned person, and the operation and maintenance shall be carried out in strict accordance with the operating procedures. When the rubber gasket to be replaced or the unglued part needs to be repaired, the fin tube shall be taken down and placed on the table to remove the old gasket, or the glue traces in the fin tube groove shall be wiped off with fine sandpaper at the unglued part, and then the oil traces in the groove shall be wiped off with carbon tetrachloride or trichloroethylene and other solvents, and then the back of the new rubber gasket shall be wiped off with fine sandpaper, and the oil traces shall also be wiped off with carbon tetrachloride or trichloroethylene solvent.Fin Tube

Then apply a thin layer of glue on the back of the groove and the rubber washer. After a little drying, the rubber washer is embedded into the groove, flattened around, and coated with talcum powder. Then, install the fin tube on the equipment rack and gently clamp it. According to the requirements of the glue specification, it can be put into operation after a period of time for the royal family of the Zhou Dynasty.